Entering Opening Retainage Balances
You use the Update Retainage screen to enter opening retainage balances, and to update retainage payable or retainage receivable.
To enter opening retainage balances:
- Project and Job Costing > PJC Transactions > Update Retainage.
- In the Retainage Number and Status fields, accept New. (If the screen does not show New in these fields, click the Create New button.)
- Enter information in the other fields above the table.
- Click Add Line, and then click Edit Details.
The Update Retainage Details screen appears.
- Enter the opening retainage balance for a contract, project, and category, and then click Save.
The detail is saved and a new blank detail appears.
- When you have finished entering details, close the Update Retainage Details screen.
- On the Update Retainage screen, click Save to add the document.
- Click Post when you are ready to post the document.